Costco – Central Point Oregon

This project was a turnkey project completed in a minimal 60 day period. This project included 24 fueling positions with Gilbarco MPDs we performed site dewatering, tank sets (three 30,000 and one 20,000 gallon tanks), product piping, doghouse set, full concrete work within our project zone, fuel island and dispenser install and startup.

The dig out for this project included an 80’ x 80’ by 17’ deep tank pit, luckily the site was large enough that we could properly slope the pit without the added need for shoring.