July 10, 2017 This project was a turnkey project completed in a minimal 60-day period. It included 24 fueling positions with Gilbarco MPDs. We performed site dewatering, tank sets (three […]

July 10, 2017

This project was a turnkey project completed in a minimal 60-day period. It included 24 fueling positions with Gilbarco MPDs. We performed site dewatering, tank sets (three 30,000- and one 20,000-gallon tank), product piping, a doghouse set, full concrete work within our project zone, fuel island and dispenser install, and startup.

The dig out for this project included an 80’ x 80’ by 17’ deep tank pit. Luckily, the site was large enough that we could properly slope the pit without the added need for shoring.