Truax – Philomath, Oregon
Our client was struggling with compliance as far as STP and UDC meeting compliance. We put a scope of work together to upgrade station with new UDC and STP sumps along with new islands and product pipe. We hit a few challenges as far as electrical with too much corrosion and had to do more excavation then planned to help and correct electrical issues. With all the challenges we were able to pull this project together in 6 weeks and open up site with complete success. Both the owner and project manager of Truax were happy as to how it all turned out and looks . Project Price $126,500